Bid 602 Swimming Pool Repair & Deck Resurfacing (Oxnard High School)

Bid Documents (Bids due October 15, 2019 at 10:00 a.m.)

             Board of Trustees Awarded to Ardalan 11/6/19

RFI 1: RFI 1: Please specify the manufacturer and model for the cast iron clean out with threaded plug & SST top per SP2.2.

Clean-out to be Model C1220-3 manufactured by MIFAB.

RFI 2: RFI 2: Please clarify if the existing floor inlets cover plates are to be replaced, Note 16 on Sheet D1.1 says “protect floor inlet fittings”; this conflicts with Detail 8 on Sheet SP2.1 which says to install new cover plate.

The body of the floor inlet that is encased in concrete is to be protected in place while the inlet cover plate that is a part of the inlet assembly is to be replaced.

RFI 3: RFI 3: Please clarify if the district is removing and storing existing deck equipment or if removal and storage is the responsibility of the contractor. I.E. bleachers, lane line reels, pool covers, water polo goals, lifeguard chairs, etc.

The contractor will be responsible for removing/relocating the 3 sheds, bleachers, covers and various other items as needed to perform the work and then return them to where they came from upon completion.

RFI 4: RFI 4: Please clarify if the district is removing the existing three (3) storage sheds from the deck prior to commencement of work.

The contractor will be responsible for removing/relocating the 3 sheds, bleachers, covers and various other items as needed to perform the work and then return them to where they came from upon completion.